Project Timeline - Updated July 2024
TIMEFRAME | MILESTONE |
Ongoing | Consultation for the Nova Solar transmission line |
Q3 2024 | Submission of Transmission Line Application to the AUC |
July-December 2024 | AUC processes Transmission Line Application |
Q4 2024 - Q1 2025 | Anticipated AUC approval and County development permits |
Q3 2025 | Start of Construction |
Mid-2027 | Construction complete; Commercial Operations Date (COD) |
Q3 - Q4 2027 | Reclamation post-construction |
*Timeline is subject to change.
**Consultation will be ongoing throughout the development, construction, operations and decommissioning phases of the Project.