Project Timeline - Updated July 2024
| TIMEFRAME | MILESTONE | 
| Ongoing | Consultation for the Nova Solar transmission line | 
| Q3 2024 | Submission of Transmission Line Application to the AUC | 
| July-December 2024 | AUC processes Transmission Line Application | 
| Q4 2024 - Q1 2025 | Anticipated AUC approval and County development permits | 
| Q3 2025 | Start of Construction | 
| Mid-2027 | Construction complete; Commercial Operations Date (COD) | 
| Q3 - Q4 2027 | Reclamation post-construction | 
*Timeline is subject to change.
**Consultation will be ongoing throughout the development, construction, operations and decommissioning phases of the Project.
 
    